IAS 23Workpapers (Step 4 of 5)

Workpaper assignment

Step 4 of 5
Mission · workpaperWorkpaper · IAS 23L3 · Advanced

Documents

Loan statement by phase

Schedule

Loan statement by phase

Loan statement by phase (15,000 EUR per month): 1 February to 31 May (4 months): 60,000 EUR; 1 June to 31 August (3 months): 45,000 EUR; 1 September to 30 November (3 months): 45,000 EUR.

Capitalisation timeline file: start, suspension and end

Construction site: start, extended interruption, temporary delays and end of inclusion

5 documents9 sections to document
0 / 6 sections completed
Guided mode

Section 1 of 9

Objective

In progress
Section brief
What to document
The engagement, its scope and the working mode chosen.
Why
A workpaper answers one precise question: framing it avoids off-topic work.
How
Read the objective and the assignment, then choose the mode (guided, semi-guided, professional).
Expected result
You know which question the workpaper must settle, and for which reporting date.
Your role
Preparer of the IAS 23 workpaper
Level
Advanced
Estimated time
≈ 60 min
Progress
0 / 5 steps done (review excluded)

Context

Constructions Aubrac SA (fictitious entity) builds a plant and its office annex, financed by a specific loan of 3,000,000 EUR at 6% per year (15,000 EUR per month), drawn on 1 February 20X5. Year end 30 November 20X5. The site experiences a three-month interruption, a rain delay and a staggered completion.

Assignment

Capitalisation timeline file

Purpose of the workpaper

For each asset under construction, describe the site, enter the expenditure, the progress payments and grants received, the duration between the start and the end of inclusion and the duration of extended suspensions, then compute the eligible expenditure and the inclusion period. Assess each interruption (extended suspension or temporary delay, substantial work) and the completion date. The borrowing costs of each phase come from the loan statement (a datum of the file).

Questions of the file covered by this workpaper

  • Do the interruption from June to August and the delay in October suspend inclusion? Justify.
  • On what date does inclusion end and what about the annex completed on 31 October? Justify.
  • Compute the eligible expenditure.
  • Compute the inclusion period.
  • Record the borrowing costs by phase and the placing in service.

Documents in the file

Open the documents to pick out the relevant information.

Choose how you want to work