IAS 23Workpapers (Step 4 of 5)

Workpaper assignment

Step 4 of 5
Mission · workpaperWorkpaper · IAS 23L4 · Expert

Documents

Engagement letter

Memo

Engagement letter

Engagement letter: file of a capitalised project of Hélios Matériaux SA (fictitious entity, ceramic tiles) for 20X5 and 20X6 (cumulative effects). Two qualifying assets are built in 20X5: a kiln, financed by a specific loan and an equipment grant, and a warehouse, financed by the general borrowings. The amounts, rates and dates are data of the file; the presentation of the grant is a choice of the entity.

Capitalisation timeline file: start, suspension and end

File of a capitalised project: capitalisation of borrowing costs, suspension, placing in service and interaction with an asset grant

7 documents8 sections to document
0 / 5 sections completed
Guided mode

Section 1 of 8

Objective

In progress
Section brief
What to document
The engagement, its scope and the working mode chosen.
Why
A workpaper answers one precise question: framing it avoids off-topic work.
How
Read the objective and the assignment, then choose the mode (guided, semi-guided, professional).
Expected result
You know which question the workpaper must settle, and for which reporting date.
Your role
Preparer of the IAS 23 workpaper
Level
Expert
Estimated time
≈ 60 min
Progress
0 / 4 steps done (review excluded)

Context

Hélios Matériaux SA (fictitious entity) builds in 20X5 two qualifying assets: a kiln, financed by a specific loan of 1,500,000 EUR and by an equipment grant of 300,000 EUR, with an interruption of two months, and a warehouse, financed by the general borrowings. The file takes the two assets through to the financial statements of 20X5 and 20X6 (cumulative effects), with the documents, the judgements, the open points and the review. Teaching simulation: the review trail of the file (preparation, reviewer notes and final sign-off) is simulated for demonstration purposes; it is neither a real review nor a validation of the content.

Assignment

Capitalisation timeline file

Purpose of the workpaper

For each asset under construction, describe the site, enter the expenditure, the progress payments and grants received, the duration between the start and the end of inclusion and the duration of extended suspensions, then compute the eligible expenditure and the inclusion period. Assess each interruption (extended suspension or temporary delay, substantial work) and the completion date. The borrowing costs of each phase come from the loan statement (a datum of the file).

Questions of the file covered by this workpaper

  • What information is missing to settle the end date of inclusion for the kiln?
  • Does the two-month interruption suspend inclusion for the kiln? Justify.
  • Compute the eligible expenditure of the kiln, net of the grant.
  • Compute the inclusion period of the kiln.
  • On what date does inclusion end for the kiln? Justify.

Documents in the file

Open the documents to pick out the relevant information.

Choose how you want to work