Document 1Contract
Construction contract
Construction contract signed on 1 March 20X1: fixed price excluding taxes 10,000,000. The warehouse is built on land owned by Logistique Cérans; the works become the customer's property as they are incorporated into the land and the customer may request changes during construction. Invoicing upon reaching technical milestones certified by the customer's architect, invoices payable within 45 days; outside these milestones, Lorvane has no right to invoice the work performed. Memo of the contract analysis team (case data): the design, construction and integration of the various work packages form a single performance obligation.