Single choiceIntermediatePublished

Question · Lower of cost and net realisable value

Vitralis is manufacturing a glass roof whose cost incurred at the reporting date amounts to EUR 1,200. Once completed, it can be sold for EUR 1,300; the remaining costs of completion are estimated at EUR 150 and the selling costs at EUR 50. At what amount is this glass roof in progress measured at the reporting date?

Your answer