Question · Specific borrowing outstanding after completion

The Hélios group financed power station C with a specific borrowing of 4,000,000. Power station C enters service on 30 June; at 31 December, 1,500,000 of that borrowing remains outstanding. Hélios is also building plant U, financed by its general borrowings. In a few sentences, justify the treatment of the 1,500,000 still outstanding in calculating the capitalisation rate for plant U.