Question · Onerous contracts and cost of fulfilling a contract

Orvande must deliver, at a fixed price of 800,000, components for which the contract provides no way out. Costs still to be incurred: incremental costs 640,000; share of the depreciation of the press used 120,000; share of the depreciation of moulds shared with other contracts 95,000; share of general administrative overheads 50,000. The shares result from the keys chosen by Orvande (case data). Compute the cost of fulfilling and the provision (no impairment of the equipment).

Fixed contract price
800,000
Incremental costs still to be incurred
640,000
Share of the depreciation of the press
120,000
Share of the depreciation of the moulds
95,000
Share of general administrative overheads
50,000