Question · Onerous contracts and cost of fulfilling a contract

In 20X6, Wavrelle must deliver parts at a total fixed price of 1,020,000; the contract contains no exit clause. The remaining cost of fulfilling, computed in accordance with the standard, is 1,150,000. No asset is used exclusively for this contract. What does Wavrelle conclude at 31 December 20X5?