CalculationAdvancedVariant — group VG.IFRS15.000202Published

Question · Contract modifications

Bâtiroc is constructing an office building on its customer's land; the contract is a single performance obligation satisfied over time, with progress measured as costs incurred relative to total expected costs. Price: EUR 1,000,000; total expected costs: EUR 800,000. At the end of 20X1, costs incurred amount to EUR 400,000 and the revenue recognised reflects progress. Early in 20X2, the parties approve a change to the plans: price increased by EUR 200,000, expected costs increased by EUR 200,000. The remaining work is not distinct from the work already performed. Compute the cumulative catch-up adjustment (decrease in revenue) recognised at the modification date.

Original contract price
1,000,000
Total expected costs before the modification
800,000
Costs incurred at the modification date
400,000
Approved price increase
200,000
Increase in expected costs
200,000