Question · Contract modifications

The Navirex shipyard is building a research vessel for an oceanographic institute. The contract is a single performance obligation satisfied over time; progress is measured using costs incurred. Agreed price: EUR 2,400,000; expected costs: EUR 1,800,000; costs incurred at 31 December 20X1: EUR 720,000. On 2 January 20X2, the institute approves the installation of an on-board laboratory integrated into the hull: the price increases by EUR 600,000 and expected costs by EUR 200,000. This work is not distinct from the vessel under construction. Compute the cumulative revenue after the modification and the cumulative catch-up adjustment (increase in revenue) recognised on 2 January 20X2.

Original contract price
2,400,000
Expected costs before the modification
1,800,000
Costs incurred at 31 December 20X1
720,000
Price increase for the laboratory
600,000
Increase in expected costs
200,000