Single choiceAdvancedPublished

Question · Contract modifications

Hydrovia is performing a civil engineering contract. The customer has approved a change of route that adds work, but still disputes the amount of the price increase claimed by Hydrovia. How does Hydrovia treat the change in price at the reporting date?

Your answer

← Back to the concept