Question · Measuring progress towards complete satisfaction

Ponts Ravel is building a bridge for a local authority, an obligation satisfied over time and measured using costs incurred. Transaction price: 2,000,000. Revenue recognised in 20X1: 800,000. At 31 December 20X2, cumulative costs incurred amount to 1,120,000 and total expected costs are revised to 1,600,000. Calculate the revenue for 20X2.

Transaction price
2,000,000
Revenue recognised in 20X1
800,000
Cumulative costs incurred at 31 December 20X2
1,120,000
Revised total expected costs
1,600,000