Journal entryIntermediateVariant — group VG.IFRS15.000504Published

Question · Measuring progress towards complete satisfaction

Mécanique Orvault is manufacturing a special press in its customer's plant, and the customer controls the construction as it progresses; the obligation is satisfied over time and progress is measured using costs. Transaction price: 600,000; total expected costs: 400,000; costs incurred at 31 December 20X1: 150,000 (already recognised as expenses). Orvault can only invoice after final acceptance of the press. Record the revenue entry at 31 December 20X1.

Transaction price
600,000
Total expected costs
400,000
Costs incurred at 31 December 20X1
150,000
Your answer
  1. Line 1

    Account Contract asset

  2. Line 2

    Account Revenue