Journal entryAdvancedVariant — group VG.IFRS15.000504Published

Question · Measuring progress towards complete satisfaction

Solaris Énergie is installing a solar power plant on land owned by a municipality, which controls the plant as it is built. Fixed price: 960,000; total expected costs, unchanged: 720,000. At the end of 20X2, cumulative costs reach 540,000; revenue recognised in 20X1 was 288,000. The contract provides for a single invoice on commissioning. Record the revenue entry for 20X2 (progress measured using costs).

Fixed price
960,000
Total expected costs
720,000
Cumulative costs at the end of 20X2
540,000
Revenue recognised in 20X1
288,000
Your answer
  1. Line 1

    Account Contract asset

  2. Line 2

    Account Revenue