For a renovation contract of Atelier Corbel (price of 1,500,000, obligation satisfied over time, progress measured using costs), an accounting assistant prepared the following at 31 December 20X2: cumulative costs 900,000; total expected costs 1,200,000; progress 75%; cumulative revenue 1,125,000; revenue recognised in 20X2: 1,125,000. Revenue for 20X1 was 450,000. Where is the error?
Single choiceAdvancedPublished