Linéo is building four assembly lines in a manufacturer's plant, and the manufacturer controls the work in progress as it is performed; the contract is a single obligation satisfied over time. At 31 December 20X1, one line is complete and delivered, and two others are almost finished in the customer's plant. The finance director proposes measuring progress by lines delivered, that is 25%. What is your assessment?