Bâtiplus is performing a contract with two performance obligations: the structural work phase, already satisfied and accepted in March 20X1, and the finishing work phase, in progress. In June 20X1, it incurs 14,000 of rework on the structural work and 6,000 of site costs for which it cannot determine whether they relate to one phase or the other. What treatment applies to these two amounts?