IFRS 15Case studies (Step 3 of 5)

Practical case

Step 3 of 5
File · Progressive casePath L1 → L4L1 · Fundamental

Corlinde Systems: the Écopôle Rivemont sorting line, from signature to the closing file

Corlinde Systems SA, a fictitious company that designs, manufactures and installs automated sorting lines for recycling centres (340 employees), IFRS financial statements, year end 31 December, amounts in euros excluding VAT unless stated otherwise.

3 documents5 tasks
0 / 5 tasks completed
Period
Year N — signature of the contract (1 February N)
Standards
IFRS 15 — Revenue from Contracts with Customers
Levels
0 / 4 levels validated
Current level
L1 · Guided≈ 90 min
Assistance levelFull guidance · strong assistance
  • Method: shown
  • Checklist: shown
  • Hints: shown
  • Step-by-step work: shown

Case brief

L1 · Guided · Year N — signature of the contract (1 February N)

Level 1 — Is there a contract, what does it promise and for what price?

On 1 February N, Corlinde Systems signs a contract with Écopôle Rivemont, a fictitious semi-public company that operates a household packaging sorting centre, for a custom-designed sorting line, manufactured in Corlinde's workshop and then installed in Écopôle's building, the training of the operators and three years of remote monitoring and maintenance, with a performance bonus. You follow this contract, from the seller's point of view, over two years and in the order of the five steps of IFRS 15: analysis of the contract and of the price at signature (level 1), allocation of the price and year-end N (level 2), amendment and completion of the line in N+1 (level 3), then the performance bonus and the N+1 closing file (level 4). All figures are case data; teaching assumptions and professional judgements are flagged as such, and no method chosen by Corlinde is presented as required by the standard. Teaching assumption: amounts are rounded to the euro and each year's entries are presented in summary form.

Standard involved: IFRS 15 Revenue from Contracts with Customers (step 1: identify the contract; step 2: identify the performance obligations; step 3: determine the transaction price). Before allocating or recognising anything, you must know which contract exists, what it promises and for what amount. Read the three documents, then answer the questions in order: each one prepares the next.

Fundamental level: the method, help and references are shown.

Method

  1. Read the brief and the assignment.
  2. Open each document and spot the relevant data.
  3. Carry out the work in the suggested order.
  4. Submit, then read the conclusion and the model answer.

File checklist

  • Open each piece (0 / 3 consulted) · to do
  • Answer the questions of the level (0 / 5) · to do
  • Validate the level, then read the conclusion · to do

Events

The file, period by period

2 / 6 stages reached

  1. Context · Dated fact of the file

    Corlinde Systems: the Écopôle Rivemont sorting line, from signature to the closing file

    Corlinde Systems SA, a fictitious company that designs, manufactures and installs automated sorting lines for recycling centres (340 employees), IFRS financial statements, year end 31 December, amounts in euros excluding VAT unless stated otherwise.

  2. Initial event · L1Year N — signature of the contract (1 February N) · Current stage

    Level 1 — Is there a contract, what does it promise and for what price?

    Standard involved: IFRS 15 Revenue from Contracts with Customers (step 1: identify the contract; step 2: identify the performance obligations; step 3: determine the transaction price). Before allocating or recognising anything, you must know which contract exists, what it promises and for what amount. Read the three documents, then answer the questions in order: each one prepares the next.

    Pieces added

    • Extract from the Corlinde – Écopôle contract (case data)
    • Additional information at 1 February N (case data)
    • Sales engineer's note on the bonus (case data)
  3. New period · L2Year N — allocation of the price and year end at 31 December N · Upcoming: unlocks after the current stage

    Upcoming stage

  4. New period · L3Year N+1 — January to May: amendment and completion of the line · Upcoming: unlocks after the current stage

    Upcoming stage

  5. New period · L4Year N+1 — performance bonus and year end at 31 December N+1 · Upcoming: unlocks after the current stage

    Upcoming stage

  6. Conclusion · Upcoming: unlocks after the current stage

    Upcoming stage

Documents

Case documents

3 documents to work from at this level.

Document 1Contract

Extract from the Corlinde – Écopôle contract (case data)

  • Signature and approval: written contract signed on 1 February N, after approval by Écopôle's board of directors on 28 January N; each party undertakes to perform its obligations.
  • Subject: (1) design of a packaging sorting line adapted to Écopôle's building and waste flows; (2) manufacture of the modules (optical sorters, conveyors, baling press) in Corlinde's workshop; (3) installation on site, connection to Écopôle's existing feed conveyors and to its supervision software, commissioning planned for 31 May N+1; (4) training of 12 operators for one week, just before commissioning; (5) 24/7 remote monitoring and monthly preventive maintenance for 3 years from commissioning.
  • Price: fixed overall price of 6,480,000 excluding tax; VAT of 20% invoiced in addition (1,296,000).
  • Performance bonus: 360,000 excluding tax if, during the 60 days of tests following commissioning, the average purity of the sorted flows reaches at least 95%; nothing otherwise (all or nothing).
  • Invoicing of the fixed price: 15% on approval of the design; 25% on factory acceptance of the modules; 30% on commissioning; 15% at the end of the tests; 15% at the start of each maintenance year (5% per year, in advance). Invoices due on receipt.
  • Termination: Écopôle may terminate at any time for convenience; it then pays Corlinde the costs incurred to date plus a margin of 15%. Corlinde may only terminate if Écopôle defaults.
  • Title: the modules remain Corlinde's property until they are delivered to the site.

Data

Facts of the file

Entity
Corlinde Systems SA, a fictitious company that designs, manufactures and installs automated sorting lines for recycling centres (340 employees), IFRS financial statements, year end 31 December, amounts in euros excluding VAT unless stated otherwise.
Period
Year N — signature of the contract (1 February N)
Current level
L1 · Guided
Standards
IFRS 15 — Revenue from Contracts with Customers

Pieces carried over from earlier levels

First level: all the data is in the brief and the pieces of this level.

Questions

5 parts to answer, marked when you submit the level.

  • Analysis and judgement2
  • Information to identify1
  • Calculations1
  • Questions1

Analysis and judgement

Set out the points for and against, then decide.

Part 1 · Multiple answers · Analysis

Step 1: which findings are correct?

Several answers may be correct: select all of them.

4 more questions will appear once the current question is complete.

Complete the question to continue.

Workspace

Your working draft for this file: points noted, leads, intermediate calculations.

Saved on this device only; never graded.

Conclusion

Answer every part to submit the level and see the conclusion.

Normative references

  • IFRS 15 §9
  • IFRS 15 §10
  • IFRS 15 §12
  • IFRS 15 §13
  • IFRS 15 §17
  • IFRS 15 §18
  • IFRS 15 §20
  • IFRS 15 §21
  • IFRS 15 §22
  • IFRS 15 §23
  • IFRS 15 §25
  • IFRS 15 §27
  • IFRS 15 §28
  • IFRS 15 §29
  • IFRS 15 §30
  • IFRS 15 §31
  • IFRS 15 §32
  • IFRS 15 §35
  • IFRS 15 §36
  • IFRS 15 §37
  • IFRS 15 §38
  • IFRS 15 §39
  • IFRS 15
  • IFRS 15 §43
  • IFRS 15 §47
  • IFRS 15 §49
  • IFRS 15 §53
  • IFRS 15 §56
  • IFRS 15 §57
  • IFRS 15 §63
  • IFRS 15 §73
  • IFRS 15 §74
  • IFRS 15 §76
  • IFRS 15 §77
  • IFRS 15 §78
  • IFRS 15 §79
  • IFRS 15 §81
  • IFRS 15 §82
  • IFRS 15 §85
  • IFRS 15 §87
  • IFRS 15 §88
  • IFRS 15 §89
  • IFRS 15 §90
  • IFRS 15 §105
  • IFRS 15 §106
  • IFRS 15 §107
  • IFRS 15 §108
  • IFRS 15 §116
  • IFRS 15 §120
  • IFRS 15 §121
  • IFRS 15 §123
  • IFRS 15 §124
  • IFRS 15 §126
  • IFRS 15 §B3
  • IFRS 15 §B8
  • IFRS 15 §B9
  • IFRS 15 §B12
  • IFRS 15 §B18
  • IFRS 15 §B19