Substantial completion
Learning objectives
- Determine the date on which capitalisation ceases (substantially all the activities necessary to prepare the asset are complete) and the transfer to the asset in use.L2, L3
- Justify and defend in a professional file (L4) the treatment adopted for the "Cessation when substantially all activities are complete" concept, distinguishing the IFRS requirement, the case data, the teaching assumption and judgement.L4
Normative references
- IAS 23 §22Capitalisation ceases when substantially all the activities necessary to prepare the asset are complete.
- IAS 23 §23An asset is normally ready for its intended use or sale when its physical construction is complete, even though routine administrative work might still continue; if only minor modifications remain (such as decoration to the purchaser's or user's specification), substantially all the activities are complete.
Original summaries of the paragraphs (reference register), never a quotation of the standard.
3 questions
- When does capitalisation of borrowing costs cease for a qualifying asset?L2
- Garance's plant is ready for its intended use: substantially all the preparation activities are complete. The cumulative cost in assets under construction comprises {construction_expenditure} of construction expenditure and {capitalised_borrowing_costs} of capitalised borrowing costs. Record the entry for entry into service.L3
- Marsac's plant, whose construction expenditure amounts to {construction_expenditure}, is financed in part by a specific loan of {principal} at {annual_rate} a year, drawn on 1 January. Substantially all the preparation activities are complete on 31 October. The year ends on 31 December: {months_until_completion} of capitalisation, then {months_after_completion} after completion. No funds are temporarily invested. Calculate the borrowing costs capitalised, those expensed, then the cost of the asset.L4
Practical cases
- Construction site: start, extended interruption, temporary delays and end of inclusionL3
- Asset financed by a specific borrowing and an asset grant: cost, depreciation, profit or loss and financial statementsL4
- File of a capitalised project: capitalisation of borrowing costs, suspension, placing in service and interaction with an asset grantL4