WorkpaperIAS 23 — Borrowing CostsL2 · L3 · L4

Capitalisation timeline file: start, suspension and end

2 missions9 sections to document60 min
Prepared by
AI-assisted draft
Reviewed by
Not reviewed — human review required
Status
Published

Objective of the workpaper

For each asset under construction, describe the site, enter the expenditure, the progress payments and grants received, the duration between the start and the end of inclusion and the duration of extended suspensions, then compute the eligible expenditure and the inclusion period. Assess each interruption (extended suspension or temporary delay, substantial work) and the completion date. The borrowing costs of each phase come from the loan statement (a datum of the file).

9 sections · 27 blocks · 2 calculations · 4 entries

  • IAS 23 §17
  • IAS 23 §18
  • IAS 23 §19
  • IAS 23 §20
  • IAS 23 §21
  • IAS 23 §22
  • IAS 23 §23
  • IAS 23 §24
  • IAS 23 §25

Work this workpaper as a mission

Each case that uses this template opens in the mission workspace: data, analysis, calculation, entries, conclusion and review, with your progress saved.

2 instances from the cases: the calculations and entries below are run by the calculation engine.

File and entity
Construction site: start, extended interruption, temporary delays and end of inclusion
Case tasks documented here
  • Do the interruption from June to August and the delay in October suspend inclusion? Justify.
  • On what date does inclusion end and what about the annex completed on 31 October? Justify.
  • Compute the eligible expenditure.
  • Compute the inclusion period.
  • Record the borrowing costs by phase and the placing in service.
1

Inputs

Inputs
  • Construction site: schedule, event log and notice of acceptance of the works

    Text

    USINE_ET_ANNEXE_FINANCEES_PAR_UN_EMPRUNT_SPECIFIQUE

  • Cash paid on the asset

    Number

    2,600,000

  • Other assets transferred for the asset

    Number

    150,000

  • Interest-bearing liabilities assumed for the asset

    Number

    250,000

  • Progress payments received for the asset

    Number

  • Grants received for the asset

    Number

  • Duration between the start and the end of inclusion (months)

    Number

    10 months

  • Duration of extended suspension periods (months)

    Number

    3 months

  • Borrowing costs of the first inclusion phase (statement by phase)

    Number

    60,000

  • Borrowing costs of the second inclusion phase (statement by phase)

    Number

    45,000

  • Borrowing costs of the suspension period (expensed)

    Number

    45,000

  • Cumulative cost of the asset under construction at completion (ledger)

    Number

    3,105,000

2

Supporting evidence

Evidence
  • Evidence obtained and referenced (category, document reference)

    EvidenceRequired

3

Analysis

Analysis

IAS 23 §17IAS 23 §18IAS 23 §19IAS 23 §20IAS 23 §21IAS 23 §22IAS 23 §23IAS 23 §24IAS 23 §25

  • Points reviewed: start, expenditure, land, suspension, end, parts

    ChecklistRequired

    • Three conditions for the start of inclusion checked
    • Eligible expenditure computed net of progress payments and grants
    • Land without development activity set aside
    • Extended interruption and exceptions assessed
    • Substantial completion assessed
    • Asset completed in parts assessed
4

Calculations

Calculations

IAS 23 §17IAS 23 §18IAS 23 §19IAS 23 §20IAS 23 §21IAS 23 §22IAS 23 §23IAS 23 §24IAS 23 §25

  • Eligible expenditure = cash + assets transferred + interest-bearing liabilities − progress payments − grants

    Calculation

    3,000,000

    Cash paid on the asset ; Other assets transferred for the asset ; Interest-bearing liabilities assumed for the asset ; − Progress payments received for the asset ; − Grants received for the asset

  • Inclusion period = duration from start to end − extended suspension

    Calculation

    7 months

    Duration between the start and the end of inclusion (months) ; − Duration of extended suspension periods (months)

5

Journal entries

Entries
  • Borrowing costs included (first phase)

    Entry

    AccountDebitCredit
    Asset under construction60,000
    Interest payable60,000
  • Borrowing costs included (second phase)

    Entry

    AccountDebitCredit
    Asset under construction45,000
    Interest payable45,000
  • Borrowing costs of the suspension, expensed

    Entry

    AccountDebitCredit
    Interest expense45,000
    Interest payable45,000
  • Placed in service: transfer of the cumulative cost

    Entry

    AccountDebitCredit
    Property, plant and equipment3,105,000
    Asset under construction3,105,000
6

Judgements

Judgment

IAS 23 §17IAS 23 §18IAS 23 §19IAS 23 §20IAS 23 §21IAS 23 §22IAS 23 §23IAS 23 §24IAS 23 §25

  • Interruption: extended suspension or temporary delay

    JudgmentRequired

    Extended suspension of active development

    Extended suspension of active development / Temporary delay inherent in the process / Substantial technical and administrative work in progress

    Rule and cross-reference: inclusion is suspended during extended periods in which active development is interrupted (IAS 23, para. 20); it is not suspended for substantial technical and administrative work or for a temporary delay inherent in the process of getting the asset ready (IAS 23, para. 21).

  • Rationale: duration, nature of the work during the interruption, cause

    TextRequired

  • Completion of the asset

    JudgmentRequired

    Substantially all activities completed

    Substantially all activities completed / Necessary activities not completed

    Rule and cross-reference: inclusion ends when substantially all the activities necessary to prepare the asset for its intended use or sale are complete (IAS 23, para. 22).

  • Rationale: end date adopted and remaining activities

    TextRequired

7

Conclusion

Conclusion
  • Dated timeline, costs included and transfer submitted to the reviewer

    ConclusionRequired

8

Effect on the financial statements

FS impact
  • Effect of the entries, line by line (derived from the entries)

    Table

9

Normative references

References
  • Paragraphs cited in this workpaper and their verification status

    References

10

Checks and financial statement impact

  • Suspension assessed and justifiedPass
  • Completion date justifiedPass
  • Transfer entry balancedPass
Assets
105,000
Liabilities
150,000
Profit or loss
-45,000
OCI
0
Equity
-45,000